Optimization of production process for resource utilization

Wybrane pełne teksty z tego czasopisma
Identyfikatory
Warianty tytułu
Języki publikacji
EN
Abstrakty
EN
The paper presents a method of scheduling execution of technological operations in work centres in a company manufacturing seats for passenger cars. To that end, an optimization algorithm based on the B&B method was developed, aimed at minimizing the number of employees necessary for operation of the work centres and at maximizing capacity of the manufacturing process. Efficiency and effectiveness of the algorithm was verified on the grounds of real data coming from the manufacturing company.
Rocznik
Strony
1251--1258
Opis fizyczny
Bibliogr. 19 poz., rys., tab.
Twórcy
  • Wroclaw University of Science and Technology, Faculty of Electronics, Department of Control Systems and Mechatronics, Janiszewskiego 11-17, 50-372 Wroclaw, Poland
autor
  • Wroclaw University of Science and Technology, Centre for Advanced Manufacturing Technologies (CAMT), Faculty of Mechanical Engineering, Lukasiewicza Street 5, 50-370 Wroclaw, Poland
  • Wroclaw University of Science and Technology, Faculty of Electronics, Department of Control Systems and Mechatronics, Janiszewskiego 11-17, 50-372 Wroclaw, Poland
  • Wroclaw University of Science and Technology, Faculty of Electronics, Telecommunications and Teleinformatics Department, Janiszewskiego 11-17, 50-372 Wroclaw, Poland
Bibliografia
  • [1] A. Ambroziak, M. Korzeniowski, Using resistance spot welding for joining aluminium elements in automotive industry, Arch. Civ. Mech. Eng. 10 (1) (2010) 5–13.
  • [2] G. Bocewicz, R. Wójcik, Z. Banaszak, Cyclic steady state refinement,Springer, International Symposium on Distributed Computing and Artificial Intelligence (2011) 191–198.
  • [3] W. Bozejko, A. Gnatowski, J. Pempera, M. Wodecki, Parallel tabu search for the cyclic job shop scheduling problem, Comput. Ind. Eng. 113 (2017) 512–524.
  • [4] W. Bozejko, Z.M. Hejducki, M. Wodecki, Applying metaheuristic strategies in construction projects management, J. Civ. Eng. Manag. 8 (5) (2012) 621–630.
  • [5] W. Bozejko, Z. Hejducki, M. Wodecki, Flowshop scheduling of construction processes with uncertain parameters, Arch. Civ. Mech. Eng. 19 (1) (2019) 194–204.
  • [6] W. Bozejko, M. Wodecki, Parallel genetic algorithm for minimizing total weighted completion time, Lect. Notes Comput. Sci. 3070 (2004) 400–405.
  • [7] W. Bozejko, J. Pempera, M. Wodecki, Minimization of the number of employees in manufacturing cells, in: M. Graña, et al. (Eds.), International Joint Conference SOCO'18-CISIS'18- ICEUTE'18, Advances in Intelligent Systems and Computing, 771, Springer, Cham, 2018.
  • [8] A. Burduk, W. Bozejko, J. Pempera, K. Musial, On the simulated annealing adaptation for tasks transportation optimization, Log. J. IGPL 26 (6) (2018) 581–592.
  • [9] A. Che, C. Chu, Multi-degree cyclic scheduling of a no-wait robotic cell with multiple robots, Eur. J. Oper. Res. 199 (1) (2009) 77–88.
  • [10] I.G. Drobouchevitch, S.P. Sethi, C. Sriskandarajah, Scheduling dual gripper robotic cell: one-unit cycles, Eur. J. Oper. Res. 171 (2) (2006) 598–631.
  • [11] J. Grabowski, J. Pempera, The permutation flow shop problem with blocking. A tabu search approach, Omega. 35 (2007) 302–311.
  • [12] B. Karwat, Optimization of production schedules in the steel production system, Arch. Civ. Mech. Eng. 12 (2) (2012) 240–252.
  • [13] E. Levner, V. Kats, V.E. Levit, An improved algorithm for cyclic flowshop scheduling in a robotic cell, Eur. J. Oper. Res. 97 (3) (1997) 500–508.
  • [14] A. Munier Kordon, A graph-based analysis of the cyclic scheduling problem with time constraints: schedulability and periodicity of the earliest schedule, J. Sched. 14 (1) (2011) 103–117.
  • [15] K. Musial, D. Górnicka, A. Burduk, Improvement of production process scheduling with the use of heuristic methods., in: A. Burduk, E. Chlebus, T. Nowakowski, A. Tubis (Eds.), Intelligent Systems in Production Engineering and Maintenance, Advances in Intelligent Systems and Computing, 835, Springer, Cham, 2018.
  • [16] J. Pempera, C. Smutnicki, Open shop cyclic scheduling, Eur. J. Oper. Res. 269 (2018) 773–781.
  • [17] D.P. Ronconi, A branch-and-bound algorithm to minimize the makespan in a flowshop with blocking, Ann. Oper. Res. 138 (2005) 53–65.
  • [18] D.P. Ronconi, A note on constructive heuristics for the flowshop problem with blocking, Int. J. Prod. Econ. 87 (2004) 39–48.
  • [19] B. Skolud, D. Krenczyk, M. Zemczak, Multi-assortment rhythmic production planning and control, IOP Conf, Ser. Mater. Sci. Eng 95 (1) (2015) 1–6, 012133.
Uwagi
PL
Opracowanie rekordu ze środków MNiSW, umowa Nr 461252 w ramach programu "Społeczna odpowiedzialność nauki" - moduł: Popularyzacja nauki i promocja sportu (2020)
Typ dokumentu
Bibliografia
Identyfikator YADDA
bwmeta1.element.baztech-ff2f6583-a958-48f3-b343-69d8e45c1d65
JavaScript jest wyłączony w Twojej przeglądarce internetowej. Włącz go, a następnie odśwież stronę, aby móc w pełni z niej korzystać.