The paper presents problems which arised in the 20-years period of exploitation of the pumped-storage power station Porąbka-Żar. It discusses also observed failings of design and construction of that object, particularly concerning the turbin sets, as well as the carried out modernizing works which improve the safety conditions of work of the station. There is also presented an analysis of damages to-the plant which occurred within the past period of exploitation of the power station and the undertaken preventive measurs.
The characteristic of the system ASTKZ of the Pilchowice dam inclusive of description of distribution and characteristic of measuring instruments have been presented. The paper presents also estimation of the work of the system in the years 1996-1997.