W artykule przedstawiono tematykę stosowania układów kontrolowanego łączenia biegunów wyłączników. Omówiono ogólne zasady działania tych układów oraz czynniki związane z poprawnością ich funkcjonowania. Zamieszczono opisy niepoprawnego działania na podstawie przykładów przekazanych przez kilku operatorów europejskich. Informacje prezentowane w artykule pochodzą z raportu ENTSO-E „Controlled switching device: application, use and maintenance problems”
EN
The article presents issues concerning controlled switching devices. The general principles of operation of these systems and factors related to their correct functioning were discussed. There are presentd descriptions of incorrect actions based on examples provided by several European operators. The information presented in the article comes from the ENTSO-E report Controlled switching device: application, use and maintenance problems
PL
Wielkoobszarowe systemy pomiarowe (WAMS – Wide Area Measurement Systems) zyskują obecnie na znaczeniu w pracującym synchronicznie, połączonym – europejskim systemie elektroenergetycznym, w którym obserwuje się rosnące obciążenie istniejącej sieci, coraz więcej obiektów wykorzystujące konwertery i silniejsze przepływy transgraniczne czy międzyregionalne. Potencjał, jaki przynoszą zsynchronizowane czasowo pomiary z PMU (Phasor Measurement Unit), ujawnia się w możliwości identyfikacji nieklasycznych zakłóceń, dla których systemy SCADA mogą być niewystarczające do wykrycia ich zaistnienia, m.in. z powodu niedostatecznej rozdzielczości pomiarowej i/lub lokalnej realizacji pomiarów. Pomiary synchrofazorowe coraz częściej służą operatorom do realizacji nowych funkcji w zakresie m.in.: monitorowania, sterowania, zabezpieczeń i analiz off-line z wykorzystaniem zsynchronizowanych danych pomiarowych. Stan obecnego wykorzystania technologii PMU w Europie i na świecie wraz z innowacyjnymi kierunkami dotyczącymi nowych możliwości ich wykorzystania, zostanie przedstawiony w niniejszym artykule, wraz ze wskazaniem planów rozwoju WAMS w KSE.
EN
Wide Area Measurement Systems (WAMS) are now gaining more and more importance in the synchronously interconnected European power system with increasing load on the existing grid, more converter-based facilities and stronger cross-border or inter-regional flows. The potential of time-synchronized measurements provided by the PMUs (Phasor Measurement Units) is revealed in the possibility of identifying non-classical disturbances for which SCADA may be insufficient to detect their occurrence, e.g. due to insufficient measurements resolution and/or their local implementation. Synchorphasor measurements are more frequently used by operators to introduce new functions for the sake of e.g. monitoring, control, protection and off-line analysis based on the synchronized measurement data. The state of the current use of PMU technology in Europe and in the world, along with innovative directions for new possibilities of their use, will be presented in this article, as well as WAMS development plans in the Polish Power System.
PL
Artykuł opisuje awarie, jakie miały miejsce w 2021 r. podczas których doszło do podziału systemów połączonych synchronicznie Europy kontynentalnej ENTSO-E. Pierwsza z nich wystąpiła 8 stycznia 2021 r., gdy wydzieliły się dwa podobszary: północno-zachodniej i południowo-wschodniej części Europy. Linia podziału obszarów przecinała sieć Operatorów Systemów Przesyłowych czterech krajów: Chorwacji (HOPS), Bośni i Hercegowiny (NOS BiH), Serbii (EMS) oraz Rumunii (Transelectrica). Druga awaria miała miejsce 24 lipca 2021 r. na połączeniu systemów operatorów Hiszpanii (REE) oraz Francji (RTE), gdzie doszło do rozdzielenia systemów energetycznych Półwyspu Iberyjskiego od pozostałej części Europy kontynentalnej. Informacje przedstawione w artykule pochodzą z raportów poawaryjnych, opracowanych przez zespół ekspertów powoływany na potrzeby przeanalizowania awarii i zbadania przyczyn ich powstania oraz opracowanie stosownych wniosków i zaleceń w celu ograniczenia możliwości powstawania podobnych awarii w przyszłości. Informacje na temat powyższych awarii były prezentowane podczas Konferencji KAE w 2022 r. Informacje o awariach są publikowane w Wiadomościach Elektrotechnicznych w oddzielnych częściach. Poniżej prezentowana jest I część artykułu, w której przedstawiono awarię z 8 stycznia 2021
EN
This article describes the events that took place in 2021, during which had place dividing of the ENTSO-E synchronously connected systems of Continental Europe. The first of them occurred on 8th January 2021, when two sub-areas were separated: north-western and south-eastern Europe. The division line of areas crossed the network of Transmission System Operators of four countries: Croatia (HOPS), Bosnia and Herzegovina (NOS BiH), Serbia (EMS) and Romania (Transelectrica). The second event took place on 24th July 2021 at the connection of the systems of the Operators of Spain (REE) and France (RTE), where went to separation the power systems of the Iberian Peninsula from the rest of Continental Europe. The information presented in the article below comes from reports developed by the Panel of Experts appointed for the purpose of analysing and examining causes of events, as well as developing conclusions and recommendations to reduce the possibility of such events in the future. Information on events published in Wiadomości Elektrotechniczny is divided on two parts. This is the first part of the article in which the event of 8th January 8 2021 is presented.
PL
W artykule przedstawiono awarię z 24 lipca 2021 r., podczas której nastąpiło oddzielenie się systemów Półwyspu Iberyjskiego od pozostałej części Europy Kontynentalnej. Prezentowane poniżej informacje pochodzą z raportu poawaryjnego, opracowanego przez zespół ekspertów, powołanego na podstawie wymagań kodeksu sieci „Wytyczne dotyczące pracy systemu przesyłowego energii elektrycznej (SO GL). W podsumowaniu zwrócono uwagę na fakt, że awarie prezentowane w obu częściach artykułu mogą stanowić ciekawy i ważny wkład w dziedzinie analizowania zagadnień związanych ze stabilnością połączonych synchronicznie systemów ENTSO-E. Podkreślono także, jak ważną rolę w ograniczeniu zasięgu i skutków awarii odgrywają zabezpieczenia reagujące na utratę synchronizmu oraz środki przewidziane w planach obrony systemów. Wskazano na znaczenie systemów monitorowania obszarowego WAMS, które mogą dostarczać informacji służbom ruchowym Operatorów o warunkach stabilności systemów i pomagać w przeciwdziałaniu pogłębiania się stanów awaryjnych.
EN
In this article is presented the event of 24th July 2021, during which the systems of the Iberian Peninsula separated from the rest of Continental Europe. The information presented in the article below comes from report developed by the Panel of Experts, established according to requirements of the network code "Guidelines for the operation of the electricity transmission system (SO GL). In the summary attention was drawn to the fact that events presented in both part of article poses an interesting and important contribution to the analysis of issues related to the stability of synchronously connected ENTSO-E systems. It was also emphasized how important role plays the protections reacting to the loss of synchronism for limitation of scale of event. There is indicated also the importance of the WAMS area monitoring systems, which can provide information to the operational services of the Operators about the system stability conditions and help prevent the deepening of emergency states.
PL
W artykule poruszono kwestie potencjalnego wpływu generacji odnawialnej wiatrowej i fotowoltaicznej, wykorzystującej układy energoelektroniczne do zasilania sieci, na poprawność funkcjonowania zabezpieczeń linii przesyłowych. Zawarte w artykule wnioski i spostrzeżenia są efektem analizy zebranych doświadczeń dotyczących powyższych zależności, jaką przeprowadził zespół specjalistów Protection Equipment, funkcjonujący w ramach struktur organizacji ENTSO-E zrzeszającej europejskich operatorów systemów przesyłowych. W pierwszej części przedstawiono podstawowe informacje dotyczące zastosowania układów energoelektronicznych w źródłach wytwórczych, których populacja jest największa w systemach europejskich. Następnie omówiono zależności dla funkcji zabezpieczeń linii przesyłowych. Na koniec załączono wnioski z ankiety ENTSO-E związanej z przedmiotowym zagadnieniem.
EN
This article describe issue of potential impact on lines protection transmission of renewables us wind and solar generation, connected to network by energoelectronic components. The conclusions and observations contained in the article are the result of the analysis of collected experience regarding the above relationships, conducted by protection specialists cooperating within the Protection Equipment Group established under ENTSO-E, an organization of European transmission system operators. On the begining article are presented basic information on the use of power electronics systems in generating sources, whose population is the largest in European systems. Next are explained the dependencies for the transmission line security function. Furhter, the conclusions of the ENTSO-E survey related to the issue were attached.