EN
The use of modern systems for initiating explosives charges should be associated with a conscious choice of millisecond delay. This is especially important when firing multi-row blasting patterns. The electronic initiation system offers great opportunities for the design and selection of millisecond delays. However, given the high precision of setting delays, its use must be well thought out. Research on the effect of millisecond delay on the frequency structure of vibrations has shown that the seismic effect significantly depends on the geological conditions, both of the deposit and the environment. It was shown that these conditions are best characterized by the analysis of vibrations induced by single explosives charges and this was the basis for the development and implementation of the signature hole (SH) method. The effectiveness of the method contributed to its application in computer programs supporting the design of blasting works. The article presents the procedure of preparing a database for the Paradigm software, based on the results of vibration analyzes recorded during the firing of single charges of explosives, taking into account the conditions related to the assessment of the impact of vibrations on buildings. The result of the program calculations is a proposal reaching even over a thousand or more combinations of delays between explosives loads and between rows of holes. Choosing the optimal solution is the most important moment in the designer’s work. It should also be remembered that the project summary should be the verification of the selected variant by measuring the vibrations and comparing the predicted effect with the real one.
PL
Stosowanie nowoczesnych systemów inicjowania ładunków materiałów wybuchowych (MW) powinno wiązać się ze świadomym wyborem opóźnienia milisekundowego. Jest to szczególnie istotne przy odpalaniu wieloszeregowych siatek strzałowych. Elektroniczny system inicjowania stwarza ogromne możliwości w zakresie projektowania i doboru opóźnień milisekundowych. Jednak biorąc pod uwagę wysoką precyzję zadawania opóźnień, jego użycie musi być dobrze przemyślane. Badania prowadzone nad wpływem opóźnienia milisekundowego na strukturę częstotliwościową drgań wykazały, że efekt sejsmiczny w istotny sposób zależy od warunków geologicznych, zarówno złoża jak i otoczenia. Wskazano, że najlepiej warunki te są charakteryzowane przez analizę drgań wzbudzanych od pojedynczych ładunków MW i to było podstawą do opracowania i wdrożenia metody signature hole (SH). Efektywność metody przyczyniła się do jej aplikacji w programach komputerowych wspomagających projektowanie robót strzałowych. W artykule przedstawiono procedurę przygotowania bazy danych dla programu Paradigm, w oparciu o wyniki analiz drgań rejestrowanych w czasie odpalania pojedynczych ładunków MW z uwzględnieniem uwarunkowań związanych z oceną oddziaływania drgań na budynki. Efektem obliczeń programu jest propozycja sięgająca nawet ponad tysiąca i więcej kombinacji opóźnień między ładunkami MW i między szeregami otworów. Wybór optymalnego rozwiązania jest najważniejszym momentem pracy projektującego. Należy również pamiętać, że podsumowaniem projektu powinna być weryfikacja wybranego wariantu przez pomiar drgań i porównanie efektu prognozowanego z rzeczywistym.
PL
W artykule przedstawiono metodykę i korzyści płynące z zastosowania nowoczesnych technologii projektowania i prowadzenia prac wiertniczo-strzałowych w odkrywkowych zakładach górniczych. Wykorzystanie synergii istniejących technologii oferowanych przez różnych producentów, takich jak np. program do optymalizacji i prowadzenia robót strzałowych O-Pitblast czy Hole Navigation System - system automatyzacji prac wiertniczych, oraz dronów pozwala nie tylko na poprawę efektywności prowadzania robót wiertniczo-strzałowych, ale także na zwiększenie bezpieczeństwa pracy.
EN
The paper presents methodology and benefits of modern blast design methods in open pit mines and quarries. Benefiting from synergy given by merging existing technologies provided by different suppliers, like blast design and optimization environment - O-Pitblast or Hole Navigation System, solution for automatized drilling of Epiroc and drones, allows not only improving efficiency of blast works but also increasing occupational health and safety.
EN
Blasting is one method of mining solid rock masses. The operation parameters, i.e. burden, blast hole and row spacing, stemming length, subdrilling length or explosive charge mass per single delay and total explosive charge mass per series, must be determined. The determined parameters can be optimized taking into account both technical and economic performance, using a dedicated software with an optimization module. The article presents different ways of improving and optimizing blasting operation parameters using O-Pitblast software and the effects of these improvements on planned blasting operations.
PL
Roboty strzałowe są jednym ze sposobów urabiania skał zwięzłych. W celu wykonania takich prac należy zaprojektować ich parametry tj. zabiór, odległość pomiędzy otworami strzałowymi i pomiędzy szeregami otworów, długość otworów strzałowych, długość przybitki, długość przewiertu czy masy ładunków materiałów wybuchowych przypadających na jedno opóźnienie oraz masę ładunku całkowitego odpalanego w serii. Wyznaczone parametry można zoptymalizować pod kątem technicznym i ekonomicznym, przy pomocy dedykowanych programów komputerowych, posiadających moduł optymalizacji. W niniejszym artykule zaprezentowano schemat postępowania w celu poprawy (optymalizacji) parametrów robót strzałowych z wykorzystaniem oprogramowania O-Pitblast, oraz efekty, jakie z tego wynikają dla zaprojektowanych robót strzałowych.
EN
Backbreak, defined as excessive breakage behind the last row of blastholes in blasting operations at a quarry, causes destabilisation of rock slopes, improper fragmentation, minimises drilling efficiency. In this paper an artificial neural network (ANN) is applied to predict backbreak, using 12 input parameters representing various controllable factors, such as the characteristics of explosives and geometrical blast design, at the Dewan Cement limestone quarry in Hattar, Pakistan. This ANN was trained with several model architectures. The 12-2-1 ANN model was selected as the simplest model yielding the best result, with a reported correlation coefficient of 0.98 and 0.97 in the training and validation phases, respectively. Sensitivity analysis of the model suggested that backbreak can be reduced most effectively by reducing powder factor, blasthole inclination, and burden. Field tests were subsequently carried out in which these sensitive parameters were varied accordingly; as a result, backbreak was controlled and reduced from 8 m to less than a metre. The resulting reduction in powder factor (kg of explosives used per m3 of blasted material) also reduced blasting costs.
PL
Kruszenie części złoża poza obszarem prowadzonych prac strzałowych oznacza nadmierne pękanie skał poza ostatnim rzędem otworów strzałowych w trakcie prac w kamieniołomach i prowadzi do destabilizacji górotworu poprzez zmianę nachylenia warstw skalnych, powoduje niepotrzebną fragmentację skał i obniża efektywność prac wiertniczych. W pracy tej wykorzystano sztuczną sieć neuronową (ANN) do przewidywania zasięgu kruszenia dalszej części złoża przy wykorzystaniu 12 parametrów wejściowych. Parametry te opisują różne zmienne czynniki, np. charakterystyka materiału wybuchowego czy przyjęty plan prac strzałowych w kamieniołomie Deewan w regionie Hattar w Pakistanie. Prowadzono proces uczenia sieci dla różnej architektury modelu, wybrano model 12-2-1 ANN, jako model najprostszy, zapewniający najlepszy wynik a współczynniki korelacji uzyskane dla fazy uczenia i walidacji wyniosły odpowiednio 0.98 i 0.97. Przeprowadzona analiza wrażliwości modelu wykazała że zasięg kruszenia dalszych części złoża obniżyć można poprzez zmianę parametrów ładunku strzelniczego, zmianę nachylenia otworów strzałowych oraz zmianę przybitki. Badania terenowe w czasie których ulegały zmianie wartości wyżej wymienionych wrażliwych parametrów wykazały, że zasięg kruszenia złoża poza obszarem prac strzałowych ograniczono z uprzednich 8 m do wielkości poniżej jednego metra. Obniżenie współczynnika charakteryzującego ładunek (kg zastosowanego materiału wybuchowego przypadający na 1 m3 rozkruszonego materiału skalnego) pozwoliło także na obniżenie kosztów prac strzałowych.