The largest bridge of the highway ring road of Wroclaw will be a cable stayed bridge over the Odra river near Rędzin stage of fall. The river flows there in its main bed, while inland navigation uses additional channel with two locks. An island with several residential buildings is located between the river and the channel. It has its own connections with mainland over the lock gates in inland navigation channel. The pylon of the new highway bridge will be placed on the island. The bridge is being erected with application of longitudinal launching method and temporary supports. Segments prefabrication is being held on three assembly stands. Maximal segments length is 32 m for viaducts and 24 for the main bridge. The pylon is being built with application of moving scaff oldings. The expected erection time is 30 months.