The objective of this paper is to analyse the time reserves in scheduling periods for conducting processes that ensure construction deadlines can be met. By using the probability account and numerical analyses methods, including ‘Monte Carlo’, execution cycles have been analysed, as well as summary stoppage times for executing teams and working areas. On the basis of calculations made using data from studies made during the construction office building in Krakow it was stated that in order to keep to the planned deadline, must be smaller periods of performance of works by individual brigades, an average of 0,103 times of rhythm.
PL
Celem jest analiza buforów czasu gwarantujących dotrzymanie planowanego terminu realizacji zadania. Z wykorzystaniem rachunku prawdopodobieństwa i metod analiz numerycznych, w tym „Monte Carlo”, zbadano okresy cykli realizacji zadań oraz sumaryczne czasy przestojów brygad wykonawczych i działek roboczych (frontów pracy). Na podstawie obliczeń danych z budowy biurowca w Krakowie stwierdzono, że dla zachowania planowanego terminu realizacji zadania, konieczne były mniejsze okresy wykonywania robót przez poszczególne brygady, średnio o 0,103 czasu trwania rytmu.
JavaScript jest wyłączony w Twojej przeglądarce internetowej. Włącz go, a następnie odśwież stronę, aby móc w pełni z niej korzystać.