The planned construction of the Central Transport Hub (CTH) requires securing vast quantities of mineral resources, particularly for the execution of large-scale earthworks. This article analyess the estimated demand for material, which, in the most likely scenario, exceeds 30 million tonnes, with the peak expected to occur in 2027-2028. An assessment was conducted to dermine the availability of mineral resources within a radius of 20-80 kilometres of the project site. The results indicate that the immediate vicinity of the CTH lacks the extraction capacity required to meet the projected demand. Effectively meeting these needs will require the exploitation of selected, currently undeveloped deposits. However, the development of these deposits is constrained by existing spatial planning regulations, which, in many cases, prevent extraction from beginning within the anticipated timeframe.