Currently, almost all medium voltage cable lines (MV) operate with the return wires earthed at both ends of the cable. Such a way of operation causes that during normal states of operation as well as during disturbances, e.g. short-circuits, in the return wires induce currents whose values mainly depend on the currents flowing in the phase wires. These currents in normal operating states are a source of additional energy losses incurred in the MV cables. The effect can be decreased by the return wires cross-bonding or the phase wires transposition. The paper discusses the potential effects that can be achieved by use of the return wires cross-bonding or the phase wires transposition in the domestic grids.
PL
Aktualnie u prawie wszystkich polskich operatorów sieci dystrybucyjnej (OSD) linie kablowe średniego napięcia (SN) pracują z żyłami powrotnymi uziemionymi na początku i na końcu linii. Taki układ pracy powoduje, że podczas stanów normalnych, jak i podczas zwarć, indukują się w żyłach powrotnych prądy, których wartości zależą głównie od prądów płynących w żyłach robo- czych. Prądy te w stanach normalnych są źródłem dodatkowych strat przesyłowych ponoszonych w kablach SN. Artykuł zawiera dyskusję nad zasadnością stosowania transpozycji żył powrotnych lub żył roboczych w warunkach krajowych.
Wydawca
Czasopismo
Rocznik
Tom
Strony
47--53
Opis fizyczny
Bibliogr. 9 poz., rys.
Twórcy
  • Gdańsk University of Technology
  • Gdańsk University of Technology
  • Gdańsk University of Technology
  • ENERGA-OPERATOR SA
autor
  • ENERGA-OPERATOR SA
  • ENERGA-OPERATOR SA
Bibliografia
  • 1. IEEE Guide for Bonding Shields and Sheaths of Single-Conductor Power Cables Rated 5 kV through 500 kV, IEEE Std 575™-2014.
  • 2. CIGRE Working group B1.18, Special bonding of high voltage power cables (2005).
  • 3. Cables and conductors of MV and LV [Kable i przewody elektroenergetyczne SN i nn], ENERGA-OPERATOR Standard, 2011.
  • 4. Cables and conductors of MV and LV [Kable i przewody elektroenergetyczne SN i nn], ENERGA-OPERATOR Standard, 2017.
  • 5. Electromobility and alternative fuels, 11 january 2018 (Ustawa z dnia 11 stycznia 2018 r. o elektromobilności i paliwach alternatywnych) [on-line], https://www.infor.pl/akt-prawny/ DZU.2018.027.0000317,ustawa-o-elektromobilnosci-i-paliwach-alternatywnych.html [acces: 10.06.2019].
  • 6. Jakubowski J., Pasniewski M., Kibler M., Cross-bonding in middle voltage distribution grids, as a method of energy efficiency improvement, 21st International Conference on Electricity Distribution, Frankfurt, Germany, 6–9 June 2011.
  • 7. Lezhniuk P.D., Pijarski P., Buslavets O. A., Smart grid technologies in local electric grids, Conference on Photonics Applications in Astronomy, Communications, Industry, and High Energy Physics Experiments, Wilga, Poland, May 28 – June 06 2017.
  • 8. Dobrzyński K. et al., Identification of the customer meter assignment to phases in LV grid. Selected issues of UPGRID project realization, 2017 IEEE 21st International Conference on Intelligent Engineering Systems (INES), Larnaca, Cyprus, 20–23 October 2017.
  • 9. Real proven solutions to enable active demand and distributed generation flexible integration, through a fully controllable LOW Voltage and medium voltage distribution grid [on-line], http://upgrid.eu [acces: 10.06.2019].