Influential factors affecting materials management in construction projects

Autorzy
Treść / Zawartość
Identyfikatory
Warianty tytułu
Języki publikacji
EN
Abstrakty
EN
Construction projects are more often than not plagued by poor performances such as delays, cost overrun, low productivity, construction wastes and compromised quality. Amongst the critical contributory factors of poor project performances, is the ineffectiveness of materials management occurring in the construction sites. Indeed, materials management is a very important component for construction projects. However, there are only limited numbers of research available regarding this topic. Thus, this research focuses its study on materials management, specifically in identifying the influential factors that affect materials management in the construction project activities. Literatures from books, journal articles and conference papers related to poor project performances and materials management have been reviewed. Consequently, this study sorted the salient influential factors and categorized them based on their specific group. Out of 47 factors identified, they are classified into 8 groups. They are (1) site condition; (2) planning and handling on site; (3) management; (4) materials; (5) supplier and manufacturer default; (6) transportation; (7) contractual; and (8) governmental interferences. In conclusion, this study contends that by identifying the influential factors affecting materials management, it will help construction players to avoid the occurrence of those factors and will minimize the negative impacts on the overall performance of construction projects. Hence, the handling-over of project will be according to schedule and not delayed by materials mismanagement.
Twórcy
autor
  • Department of Construction Management, Faculty of Technology Management and Business, Universiti Tun Hussein Onn Malaysia, Malaysia
autor
  • Faculty of Technology Management and Business, Universiti Tun Hussein Onn Malaysia 81400 Parit Raja, Johor, Malaysia
Bibliografia
  • [1] Ibrahim A.R., Roy M.H., Ahmed Z., Imtiaz G., An investigation of the status ofthe Malaysian construction industry, Benchmarking: An Int. J., 17, 4, 263-270, 2010.
  • [2] Nwachukwu C.C., Emoh F.I., A systems approach in analysing material constraining factors to construction project management success in Nigeria, Interdisciplinary J. of Contemporary Research in Business, 2, 5, 90-105, 2010.
  • [3] Winch G.M., Managing construction projects – an information processing approach, (2nd ed.), West Sussex: John Wiley & Sons, Ltd, 2010.
  • [4] Hughes R., Thorpe D., A review of enabling factors in construction industry productivity in an Australian environment, Construction Innovation: Information, Process, Management, 14, 2, 210-228, 2014.
  • [5] Yong Y.C., Mustaffa N.E., Analysis of factors critical to construction project success in Malaysia, Engineering, Construction and Architectural Management, 19, 5, 543-556, 2012.
  • [6] Khan R.A., Liew M.S., Ghazali Z., Malaysian construction sector and Malaysia vision 2020: developed nation status, Procedia-Social and Behavioral Sciences, 109, 507-513, 2014.
  • [7] Abu Mansor S., The 7th Malaysia construction sector review and outlook seminar, http://www.kkr. gov.my/files/PRESSCIDB 3 Ogos 0.pdf, pp. 1-7, 2010.
  • [8] Shehu Z., Holt G.D., Endut I.R., Akintoye A., Analysis of characteristics affecting completion time for Malaysian construction projects, Built Environment Project and Asset Management, 5, 1, 52-68, 2015.
  • [9] Fewings P., Construction project management – an integrated approach, (2nd ed.), Oxon. Routledge, 2012.
  • [10] Smith N.J., Merna T., Jobling P., Managing risk in construction projects, (3rd ed.), West Sussex: John Wiley & Sons Ltd., 2014.
  • [11] Shehata M.E., El-Gohary K.M., Towards improving construction labor productivity and projects’ performance, Alexandria Engineering J., 50, 4, 321-330, 2011.
  • [12] Meng X., The effect of relationship management on project performance in construction, Int. J. of Project Management, 30, 2, 188-198, 2012.
  • [13] Nagapan S., Abdul Rahman I., Asmi A., Factors contributing to physical and non-physical waste generation in construction industry, Int. J. of Advances in Applied Sciences, 1, 1, 1-10, 2012.
  • [14] Doloi H., Sawhney A., Iyer K.C., Rentala S., Analysing factors affecting delays in Indian construction projects, Int. J. of Project Management, 30, 4, 479-489, 2012.
  • [15] Abdul Rahman I., Memon A.H., Azis A., Asmi A., Abdullah N.H., Modeling causes of cost overrun in large construction projects with partial least squareSEM approach: contractor’s perspective, Research J. of Applied Sciences, Engineering and Technology, 5, 6, 1963-1972, 2013.
  • [16] El-Gohary K.M., Aziz R.F., Factors influencing construction labor productivity in Egypt, J. of Management in Engineering, 30, 1, 1-9, 2014.
  • [17] Rivas R.A., Borcherding J.D., González V., Alarcón L.F., Analysis of factors influencing productivity using craftsmen questionnaires?: case study in a Chilean construction company, J. of Construction Engineering and Management, 137, 4, 312-320, 2010.
  • [18] Safa M., Shahi A., Haas C.T., Hipel K.W., Supplier selection process in an integrated construction materials management model, Automation in Construction, 48, 64-73, 2014.
  • [19] Caldas C.H., Menches C.L., Reyes P.M., Navarro L., Vargas D.M., Materials management practices in the construction industry, Practice Periodical on Structural Design and Construction, pp. 1-8, 2014.
  • [20] Abdul Rahman H., Alidrisyi M.N., A perspective of material management practices in a fast developing economy: the case of Malaysia, Construction Management and Economics, 12, 5, 413-422, 1994.
  • [21] Kasim N., Ern P.A.S., The awareness of ICT implementation for materials management in construction projects, Int. J. of Computer and Communication Technology, 2, 1, 1-10, 2010.
  • [22] Kasim N., ICT implementation for materials management in construction projects?: case studies, KICEM J. of Construction Engineering and Project Management, pp. 31-36, 2011.
  • [23] Bell L.C., Stukhart G., Attributes of materials management systems, J. of Construction Engineering and Management, 112, 1, 14-21, 1986.
  • [24] Chitkara K.K., Construction project management: planning, scheduling and controlling, New Delhi: Tata McGraw-Hill Publishing Company Ltd., 1998.
  • [25] Benton W.C., McHenry L., Construction purchasing & supply chain management, New York: The McGraw-Hill Companies, Inc., 2010.
  • [26] Del Pico W.J., Project control-integrating cost and schedule in construction, New Jersey: John Wiley & Sons, Inc., 2013.
  • [27] Othman I., Napiah M., Potty N.S., Resource management in construction project, Applied Mechanics and Materials, 567, 607-612, 2014.
  • [28] Said H., El-Rayes K., Optimal material logistics planning in congested construction sites, Construction Research Congress 2012 c ASCE 2012, pp. 1580-1589, 2012.
  • [29] Cooke B., Williams P., Construction planning, programming and control, (3rd ed.), West Sussex: Wiley-Blackwell, 2009.
  • [30] Mincks W.R., Johnston H., Construction jobsite management, (3rd ed.), New York: Delmar Cengage Learning, 2011.
  • [31] Johnston J.E., Site control of materials – handling, storage and protection, London, Butterworths, 1981.
  • [32] Kazaz A., Manisali E., Ulubeyli S., Effect of basic motivational factors on construction workforce productivity in Turkey, J. of Civil Engineering and Management, 14, 2, 95-106, 2008.
  • [33] Kaming P.F., Olomolaiye P.O., Holt G.D., Harris F.C., Factors influencing craftsmen’s productivity in Indonesia, Int. J. of Project Management, 15, 1, 21-30, 1997.
  • [34] Jarkas A.M., Bitar C.G., Factors affecting construction labor productivity in Kuwait, J. of Construction Engineering and Management, 138, 7, 811-820, 2011.
  • [35] Patil A.R., Pataskar S.V., Analyzing material management techniques on construction project, Int. J. of Engineering and Innovation Tech., 3, 4, 96-100, 2013.
  • [36] Potty N.S., Irdus A., Ramanathan C.T., Case study and survey on time and cost overrun of multiple D&B projects, 2011 National Postgraduate Conference, pp. 1-6, 2011.
  • [37] Durdyev S., Mbachu J., On-site labour productivity of New Zealand construction industry?: key constraints and improvement measures, Australasian J. of Construction Economics and Building, 11, 3, 18-33, 2011.
  • [38] Wan S.K., Kumaraswamy M.M., Industrial management approaches for improving material control in building services works, Engineering, Construction and Architectural Management, 16, 3, 208-223, 2009.
  • [39] Osmani M., Glass J., Price A.D.F., Architects’ perspectives on construction waste reduction by design, Waste Management, 28, 7, 1147-1158, 2008.
  • [40] Toor S.U.R., Ogunlana S.O., Problems causing delays in major construction projects in Thailand, Construction Management and Economics, 26, 4, 395-408, 2008.
  • [41] Sambasivan M., Soon Y.W., Causes and effects of delays in Malaysian construction industry, Int. J. of Project Management, 25, 5, 517-526, 2007.
  • [42] Tam V.W., Shen L.Y., Fung I.W., Wang J.Y., Controlling construction waste by implementing governmental ordinances in Hong Kong, Construction Innovation, 7, 2, 149-166, 2007.
  • [43] Enshassi A., Mohamed S., Abu Mustafa Z., Mayer P.E., Factors affecting labour productivity in building projects in the Gaza strip, J. of Civil Engineering and Management, 13, 4, 245-254, 2007.
  • [44] Navon R., Berkovich O., Automated materials management and control model, Construction Research Congress 2005, pp. 287-295, 2005.
  • [45] Assaf S.A., Al-Hejji S., Causes of delay in large construction projects, Int. J. of Project Management, 24, 4, 349–357, 2006.
  • [46] Osmani M., Glass J., Price A.D., Architect and contractor attitudes to waste minimization, Proceeding of the Institution of Civil Engineers: Waste and Resource Management, 159, 65-72, 2006.
  • [47] Abdul Kadir M.R., Lee W.P., Jaafar M.S., Sapuan S.M., Ali A., Factors affecting construction labour productivity for Malaysian residential projects, Structural Survey, 23, 1, 42-54, 2005.
  • [48] Ekanayake L.L., Ofori G., Building waste assessment score: design-based tool, Building and Environment, 39, 7, 851-861, 2004.
  • [49] Manavazhi M.R., Adhikari D.K., Material and equipment procurement delays in highway projects in Nepal, Int. J. of Project Management, 20, 8, 627-632, 2002.
  • [50] Odeh A.M., Battaineh H.T., Causes of construction delay: traditional contracts, Int. J. of Project Management, 20, 1, 67-73, 2002.
  • [51] Makulsawatudom A., Emsley M., Factors affecting the productivity of the construction industry in Thailand: the project managers’ perception, 17th Annual ARCOM Conference, 1, 281-290, 2001.
  • [52] Zakeri M., Olomolaiye P.O., Holt G.D., Harris F.C., A survey of constraints on Iranian construction operatives’ productivity, Construction Management and Economics, 14, 5, 417-426, 1996.
  • [53] Ogunlana S.O., Promkuntong K., Jearkjirm V., Construction delays in a fast-growing economy: comparing Thailand with other economies, Int. J. of Project Management, 14, 1, 37-45, 1996.
  • [54] Abdul Majid M., McCaffer R., Factors of nonexcusable delays that influence contractors’ performance, J. of Management in Engineering, 14, 3, 42-49, 1998.
  • [55] Guo J., Construction materials management system design based on barcode, Advanced Materials Research, 860, 2825-2829, 2014.
  • [56] Dey P.K., Re-engineering materials management: a case study on an Indian refinery, Business Process Management Journal, 7, 5, 394-408, 2001.
  • [57] Ibn-homaid N.T., A comparative evaluation of construction and manufacturing materials management, Int. J. of Project Management, 20, 4, 263-270, 2002.
  • [58] Barriga E., Jeong J., Material requirements planning for a manufactured housing facility, J. of Architectural Engineering, 11, 3, 91-98, 2005.
  • [59] Akintoye A., Just-in-Time application and implementation for building material management, Construction Management and Economics, 13, 2, 105-113, 1995.
  • [60] Fawcett S., Birou L., Just-in-time sourcing techniques: current state of adoption and performance benefits, Production and Inventory Management J., 34, 18-18, 1993.
  • [61] Ng S.T., Shi J., Fang Y., Enhancing the logistics of construction materials through activity-based simulation approach, Engineering, Construction and Architectural Management, 16, 3, 224-237, 2009.
Uwagi
Opracowanie w ramach umowy 509/P-DUN/2018 ze środków MNiSW przeznaczonych na działalność upowszechniającą naukę (2018).
Typ dokumentu
Bibliografia
Identyfikator YADDA
bwmeta1.element.baztech-e823e7f6-d88f-48d7-963f-501545822641
JavaScript jest wyłączony w Twojej przeglądarce internetowej. Włącz go, a następnie odśwież stronę, aby móc w pełni z niej korzystać.