An application of reinforced concrete vaulted slabs and rafts in deep excavation works

Treść / Zawartość
Identyfikatory
Warianty tytułu
PL
Zastosowanie żelbetowych płyt sklepionych podczas wykonywania głębokich wykopów
Języki publikacji
EN
Abstrakty
EN
The overall efficiency of a construction of a deep excavation urban project does not depend only on the duration of the construction but also on its influence on the urban environment and the traffic [9, 10]. These two things depend greatly on the excavation method and the construction stages defined during the design process. This paper describes the construction stages of three metro stations (two stations in Warsaw and one in Paris) and discusses their advantages and disadvantages including among other things its impact on neighbouring infrastructure and the city’s traffic. An important conclusion drawn from this analysis is that the shape of the slabs used can considerably affect the design and the construction stages. For example, a vaulted top slab allows an almost immediate traffic restoration and a vaulted bottom raft allows a much shorter dewatering period.
PL
Ogólna efektywność budowy miejskiej inwestycji głębokiego wykopu nie zależy tylko od czasu trwania budowy, ale także od jej wpływu na środowisko miejskie i ruch drogowy [9, 10]. Te dwie rzeczy zależą w dużej mierze od metody wykopów i etapów budowy określonych w procesie projektowania. W niniejszym opracowaniu opisano etapy budowy trzech stacji metra (dwóch w Warszawie i jednej w Paryżu) oraz omówiono ich zalety i wady, w tym m.in. wpływ na sąsiadującą infrastrukturę i ruch w mieście. Ważnym wnioskiem wynikającym z tej analizy jest to, że kształt zastosowanych płyt może mieć istotny wpływ na projekt i etapy budowy. Na przykład, górna płyta sklepiona pozwala na niemal natychmiastowe przywrócenie ruchu, a dolna płyta sklepiona pozwala na znacznie krótszy okres odwadniania. W rezultacie powstała bardziej globalna dyskusja na temat interakcji konstrukcji z gruntem, gdzie wykorzystywane są sklepione elementy konstrukcyjne. Gdy nacisk gruntu jest wywierany na sklepione górną płytę lub płytę denną, tworzenie się sił obręczowych w betonowych przekrojach poprzecznych pozwala na dodatkowe przenoszenie obciążeń i tym samym oferuje znaczne korzyści i szerokie możliwości projektowe.
Rocznik
Strony
61--75
Opis fizyczny
Bibliogr. 10 poz., il., tab.
Bibliografia
  • [1] A. Stańczyk, “Doświadczenia z budowy stacji metra "Ratusz" i "Marymont" w Warszawie”, Inżynieria i Budownictwo, 5, pp. 244-247, 2008.
  • [2] Daktera, T., Bourgeois, E., Schmitt, P., Jeanmaire, T., Delva, L., & Priol, G., “Design of deep supported excavations: comparison between real behavior and predictions based on the subgrade coefficient method”, Proceedings of the XVII European Conference on Soil Mechanics and Geotechnical Engineering, pp. 2608-2615, 2019.
  • [3] Daktera T. “Amélioration des méthodes de calcul des écrans de soutènement à partir du retour d'expérience de grands travaux récents » PhD Thesis, Univ Gustave Eiffel, (to be published) 2020.
  • [4] M. Graff, “Subway in Warsaw”, Transport systems, 12, pp. 25-35, 2018.
  • [5] K.F. Unrug, “Shaft design criteria”, International Journal of Mining Engineering, 2, 141-155, 1984.
  • [6] ILF CONSULTING ENGINEERS, “Design and construction of the underground line II from “Rondo Daszyńskiego” station to the “Dworzec Wileński” station in Warsaw”, 2010.
  • [7] M. Mitew-Czajewska, “Geotechnical investigation and static analysis of deep excavation walls - a case study of metro station construction in Warsaw”, Ann. Warsaw Univ. Life Sci. - SGGW, Land Reclam. 47 (2), pp. 163-171, 2015. http://doi.org/10.1515/sggw-2015-0022
  • [8] A. Sieminska-Lewandowska, “Budowa obiektu a obudowa wykopu - niełatwe zależności”, Nowoczesne Budownictwo Inżynieryjne, marzec kwiecień, pp. 64-71, 2010.
  • [9] A. Siemińska-Lewandowska, “Głębokie wykopy. Projektowanie i wykonawstwo”. WKŁ, Warszawa, 2010.
  • [10] G. Kacprzak, S. Bodus, “The modelling of excavation protection in a highly urbanised environment”, Technical Transactions, Vol. 1, pp. 133-142, 2019. https://doi.org/10.4467/2353737XCT.19.009.10049
Uwagi
Opracowanie rekordu ze środków MNiSW, umowa Nr 461252 w ramach programu "Społeczna odpowiedzialność nauki" - moduł: Popularyzacja nauki i promocja sportu (2021).
Typ dokumentu
Bibliografia
Identyfikator YADDA
bwmeta1.element.baztech-dadb1ac9-5ae3-4e0e-a207-9064d78454d4
JavaScript jest wyłączony w Twojej przeglądarce internetowej. Włącz go, a następnie odśwież stronę, aby móc w pełni z niej korzystać.