A customized root cause analysis approach for cost overruns and schedule slippage in paper-machine-building projects

Treść / Zawartość
Identyfikatory
Warianty tytułu
Języki publikacji
EN
Abstrakty
EN
This study presents a customized root cause analysis approach to investigate the reasons, provide improvements measures for the cost overruns, and schedule slippage in papermachine-building projects. The proposed approach is an analytical-survey approach that uses both actual technical data and experts’ opinions. Various analysis tools are embedded in the approach including: data collection and clustering, interviews with experts, 5-Whys, Pareto charts, cause and effect diagram, and critical ratio control charts. The approach was implemented on seven projects obtained from a leading international paper machine supplier. As a result, it was found that the main causes behind cost and schedule deviations are products’ related; including technical accidents in the Press section, damaged parts, design issues, optimization of the machine and missing parts. Based on the results, prevention measures were perceived.
Twórcy
  • Korn Ferry Consulting, Organization Strategy Solution, Dubai, United Arab Emirates
  • German Jordanian University, Industrial Engineering Department, 11180 Amman, Jordan
Bibliografia
  • [1] Ahsan K., Gunawan I., Analysis of cost and schedule performance of international development projects, Int. J. Proj. Manag., 28, 68–78, 2010.
  • [2] Rao N.S., Jigeesh N., A study of reasons behind delays in pharmaceutical projects, IUP J. Oper. Manag., 11, 19–28, 2012.
  • [3] Pimchangthong D., Boonjing V., Effects of risk management practices on it project success, Manag. Prod. Eng. Rev., 8, 1, 30–37, 2017.
  • [4] Assaf S.A., Al-Hejji S., Causes of delay in large construction projects, Int. J. Proj. Manag., 24, 349–357, 2006.
  • [5] Ramanathan C., Narayanan S.P., Idrus A.B., Construction delays causing risks on time and cost – a critical review, Const. Eco. Build., 12, 37–57, 2012.
  • [6] Love P.E., Smith J., Simpson I., Regan M., Olatunji O., Understanding the landscape of overruns in transport infrastructure projects, Envi. Plan. B: Plan. Des., 42, 490–509, 2015.
  • [7] Love P.E., Sing C.P., Wang X., Edwards D.J., Odeyinka H., Probability distribution fitting of schedule overruns in construction projects, J. Oper. Res. Soc., 64, 1231–1247, 2013.
  • [8] Flyvbjerg B., Skamris M.K., Buhl S.L., How common and how large are cost overruns in transport infrastructure projects?, Trans. Rev., 23, 71–88, 2003.
  • [9] Chan D.W., Kumaraswamy M.M., A comparative study of causes of time overruns in Hong Kong construction projects, Int. J. Proj. Manag., 15, 55–63, 1997.
  • [10] Kaming P.F., Olomolaiye P.O., Holt G.D., Harris F.C., Factors influencing construction time and cost overruns on high-rise projects in Indonesia, Const. Manag. Eco., 15, 83–94, 1997.
  • [11] Frimpong Y., Oluwoye J., Crawford L., Causes of delay and cost overruns in construction of groundwater projects in a developing country; Ghana as a case study, Int. J. Proj. Manag., 21, 321–326, 2003.
  • [12] Memon A.H., Rahman I.A., Azis A.A., Preliminary study on causative factors leading to construction cost overrun, Int. J. Sust. Const. Eng. Technol., 2, 57–71, 2011.
  • [13] Bellmann J., Knorr A., Schomaker R., Factors influencing time and cost overruns in aircraft projects, J. Air Trans. Avi. Bus. Stud. Profess., 18, 1–4, 2011.
  • [14] Arshad T., Cost and schedule overrun in naval shipbuilding, from: https://tkays.com/2012/11/06/costoverrun-in-naval-shipbuilding-2/ accessed September 6, 2018.
  • [15] CEPI, Outlook for the world paper grade pulp market, from: http://www.cepi.org/system/files/public/documents/events/EuropeanPaperWeek2015/Schaeffer%20-%20RISI.pdf accessed September 6, 2018.
  • [16] Masternak-Janus A., Rybaczewska-Błażejowska M., Life cycle analysis of tissue paper manufacturing from virgin pulp or recycled waste paper, Manag. Prod. Eng. Rev., 6, 3, 47–54, 2015.
  • [17] Bajpai P., Brief description of the pulp and paper making process, [in:] Biotechnology for pulp and paper processing, Springer, New York, USA, 2012.
  • [18] CPI, Papermaking process, from: http://www.paper.org.uk/information/process/machine.html accessed September 6, 2018.
  • [19] Paperonline, Papermaking, from: http://www.paperonline.org/paper-making/paper-production/papermaking accessed June 1, 2017.
  • [20] Doggett A.M., Root cause analysis: a framework for tool selection, Qual. Manag. J., 12, 34–45, 2005.
  • [21] Latino R.J., Latino K.C., Latino M.A., Root cause analysis: improving performance for bottom-line results, CRC press, Florida, USA, 2011.
  • [22] Wilkinson L., Revising the Pareto chart, Ameri. Statist., 60, 332–334, 2006.
  • [23] Nagi A., Altarazi S., Integration of value stream map and strategic layout planning into DMAIC approach to improve carpeting process, J. Ind. Eng. Manag., 10, 74–97, 2017.
  • [24] Meredith J.R., Mantel Jr S.J., Shafer S.M., Project management: a managerial approach, John Wiley & Sons, 2017.
  • [25] Iyer K.C., Jha K.N., Factors affecting cost performance: evidence from Indian construction projects, Int. J. Proj. Manag., 23, 283–295, 2005.
  • [26] Boyer K.K., Swink M.L., Empirical elephants – why multiple methods are essential to quality research, J. Oper. Manag., 26, 337–348, 2008.
  • [27] Yin R.K., Case study research: design and methods, Sage publications, California, USA, 2013.
  • [28] Al-Ahmad W., Al-Fagih K., Khanfar K., Alsamara K., Abuleil S., Abu-Salem H., A taxonomy of an IT project failure: root causes, Int. J. Manag. Rev., 5, 93–104, 2009.
  • [29] Whitney K.M., Daniels C.B., The root cause of failure in complex IT projects: complexity itself, Proc. Comput. Sci., 20, 325–330, 2013.
  • [30] Flyvbjerg B., Skamris Holm M.K., Buhl S.L., What causes cost overrun in transport infrastructure projects?, Transp. Rev., 24, 3–18, 2004.
  • [31] Westerveld E., The project excellence model: linking success criteria and critical success factors, Int. J. Proj. Manag., 21, 411–418, 2003.
Uwagi
Opracowanie rekordu ze środków MNiSW, umowa Nr 461252 w ramach programu "Społeczna odpowiedzialność nauki" - moduł: Popularyzacja nauki i promocja sportu (2020).
Typ dokumentu
Bibliografia
Identyfikator YADDA
bwmeta1.element.baztech-b6fb0289-4377-4b0c-a61f-8a98306c6c09
JavaScript jest wyłączony w Twojej przeglądarce internetowej. Włącz go, a następnie odśwież stronę, aby móc w pełni z niej korzystać.