Tytuł artykułu

Modelowanie sił tarcia w instalacjach metodami HDD oraz formowalnych wykładzin w mikrotunelowaniach na długich dystansach

Wybrane pełne teksty z tego czasopisma
Identyfikatory
Warianty tytułu
EN
Modelling of HDD Pipeline Frictional Resistance, and Extruded Microtunnelling Linings for Long-Distance 'Cable Pipe' Installations
Języki publikacji
PL
Abstrakty
EN
The supply of power to the major centres of population must be assured to satisfy economic and social demands. Small-scale local generation plant, such as roof-mounted wind generators and solar panels, might play a part, but it is clear that large-scale electrical power generation will be required to supply the base load. The next generation of major power stations of any form will inevitably be built away from the major urban areas, and indeed many of the best sites are on the coast or off shore, often in very remote locations. Long transmission lines are thus inevitable, and are an indispensable component of a sustainable electricity supply in the 21st century. It is considered desirable to dispense with pylon-mounted overhead cables for electricity distribution and thus economic burial methods must be sought.
Rocznik
Tom
Strony
74--80
Opis fizyczny
Bibliogr. 11 poz., rys., tab., wykr.
Twórcy
autor
autor
autor
autor
autor
  • Uniwersytet Birmingham, Wielka Brytania
Bibliografia
  • [1] POST (2007): “POSTNOTE: Electricity in the UK.” Parliamentary Office of Science and Technology, February 2007, POSTNOTE No. 280. Online Report (Last accessed June 2007). http://www.iop.org/activity/policy/Publications/file_21079.pdf
  • [2] BBC (2006): “Council Objects to Pylon Proposal.” British Broadcasting Corporation Online news report. (Last accessed June2007). http://news.bbc.co.uk/1/hi/scotland/tayside_and_central/4974504.stm
  • [3] OWEN (2007): “Offshore Wind Energy in the UK.” The Offshore Wind Energy Network, Online (Last accessed June 2007). http://www.owen.eru.rl.ac.uk/
  • [4] McKenna, J.: “Power lines to hang over Olympic Park until 2009” New Civil Engineer, p10, Issue Date 13th April 2006
  • [5] Kotsikos, G. (2006): “Personnel Communications.” Dr G. Kotsikos, Newcastle University
  • [6] Royal, A. C. D., Rogers, C. D. F. and Chapman, D. N. (2006): “Installation of Cables Over Long Distances Using Trenchless Techniques.” Proceedings of the 24th International Conference on Trenchless Installation of Utilities No Dig Conference, Brisbane, Australia, 29 Oct - 2 Nov.
  • [7] Royal, A. C. D., Rogers, C. D. F. and Chapman, D. N. (2006): “Practical Limitations of Traditional Trenchless Technologies for Long-Distance High Voltage Cable Installation.” Online Proceedings of the No Dig Live Conference, Coventry, September 26-28. (Last accessed October 2006) http://www.nodiglive-pipelines.com/conferencepapers
  • [8] Cheng, E. and Polak, M. A. (2005): “Modelling Installation Loads for Pipe In Horizontal Directional Drilling.” Proceedings of International No-Dig 2005, Rotterdam, The Netherlands.
  • [9] Lasheen, A. and Polak, M. A. (2001): “Predicting the Behaviour of HDPE Pipes in Horizontal Directional Drilling.” Underground Infrastructure Research: Municipal, Industrial and Environmental Applications. Edited by Knight, M. and Thomson, N. A. A Balkema Publishers ISBN 90 2651 820 X
  • [10] Fourie, B. (2004): “TunnelTEQ system for Wellington.” Australasian society for trenchless technology ASTT, newsletter, March 2004, 12 pp.
  • [11] SA (2007): “Extruded Concrete Lining Method.” Shield Tunnelling Association of Japan. Online Report (Last accessed June 2007). http://www.shield-method.gr.jp/english/ecl/index.html
Typ dokumentu
Bibliografia
Identyfikator YADDA
bwmeta1.element.baztech-article-BWAK-0010-0021
JavaScript jest wyłączony w Twojej przeglądarce internetowej. Włącz go, a następnie odśwież stronę, aby móc w pełni z niej korzystać.