An evaluation of project completion with application of fuzzy set theory

Autorzy
Wybrane pełne teksty z tego czasopisma
Identyfikatory
Warianty tytułu
PL
Ocena realizacji przedsięwzięcia z wykorzystaniem teorii zbiorów rozmytych
Języki publikacji
EN
Abstrakty
EN
The project management contains such elements as management of time, cost, communications, procurement, quality, risk or scope of project. Each of these fields can be considered as a set of constraints, and then there is a possibility to verify their fulfillment in sense of an enterprise's constraints and its environment. These constraints determine a completion of project activities and its success or failure, finally. The paper aims to present a problem of project management in terms of fuzzy constraints satisfaction problem, and then the using of constraint programming techniques to the evaluation of project completion. A fuzzy constraints satisfaction problem enables a description of data in distinct, as well as imprecise form, in a unified framework. It seems especially important in case of unique activities of project, when their estimation is based on linguistic information from experts.
PL
W ramach zarządzania przedsięwzięciem wymienia się najczęściej takie elementy jak zarządzanie czasem, kosztami, komunikacją, dostawami, jakością, ryzykiem czy zakresem projektu. Każdy z tych obszarów zarządzania projektem można rozpatrywać w postaci zbioru ograniczeń, a następnie sprawdzać ich spełnienie w aspekcie ograniczeń wynikających z charakteru przedsiębiorstwa wdrażającego przedsięwzięcie oraz jego otoczenia. Ograniczenia te determinują realizację poszczególnych czynności projektu i ostatecznie to czy zakończy się on sukcesem, czy niepowodzeniem. Celem pracy jest przedstawienie problemu zarządzania przedsięwzięciem w postaci rozmytego problemu spełniania ograniczeń, a następnie wykorzystanie technik programowania z ograniczeniami do oceny realizacji przedsięwzięcia. Rozmyty problem spełniania ograniczeń umożliwia wyrażenie danych tak w postaci precyzyjnej, jak i nieprecyzyjnej w ramach jednego podejścia. Wydaje się to szczególnie istotne w przypadku planowania realizacji czynności unikalnych projektu, gdy ich szacowanie jest dokonywane przede wszystkim w oparciu o opinie ekspertów.
Czasopismo
Rocznik
Strony
216--229
Opis fizyczny
Bibliogr. 19 poz., rys.
Twórcy
autor
Bibliografia
  • 1. Bocewicz G., Bach-Dąbrowska I., Banaszak Z. (2009), Deklaratywne projektowanie systemów komputerowego wspomagania planowania przedsięwzięć, Akademicka Oficyna Wydawnicza EXIT, Warszawa.
  • 2. Bubnicki Z. (1998), Logic-algebraic method for knowledge-based relation systems, Systems Analysis Modelling and Simulation, vol. 33, ss. 21-35.
  • 3. Bubnicki Z. (1999), Procesy uczenia i metoda logiczno-algebraiczna w systemach z reprezentacją wiedzy, Analiza systemowa i zarządzanie, Instytut Badań Systemowych PAN, Warszawa.
  • 4. Dubois D., Fargier H., Fortemps P. (2003), Fuzzy scheduling: modeling flexible constraints vs. coping with incomplete knowledge, European Journal of Operational Research, no. 147, ss. 231-252.
  • 5. Hooker J.N. (2002), Logic, optimisation and constraint programming, Journal on Computing, vol. 14, ss. 295-321.
  • 6. Kerzner H. (2009), Project Management: A Systems Approach to Planning, Scheduling, and Controlling, 10th ed., John Wiley and Sons.
  • 7. Łęski J. (2008), Systemy neuronowo-rozmyte, WNT, Warszawa.
  • 8. Nitithamyong P., Skibniewski M.J. (2006), Success/failure factors and performance measures of web-based construction project management systems: professionals' viewpoint, Journal of Construction Engineering and Management, vol. 132, ss. 80-87.
  • 9. Piegat A. (2003), Modelowanie i sterowanie rozmyte, Akademicka Oficyna Wydawnicza EXIT.
  • 10. Relich M. (2011), Project prototyping with application of CP-based approach, Management, vol. 15, no 2, ss. 364-377.
  • 11. Robertson S., Williams T. (2006), Understanding project failure: using cognitive mapping in an insurance project, Project Management Journal, vol. 37, ss. 55-71.
  • 12. Rossi F. (2000), Constraint (logic) programming: A survey on research and applications, K.R. Apt i in. (red.), New Trends in Constraints, Springer-Verlag, Berlin, ss. 40-74.
  • 13. Rutkowska D., Piliński M., Rutkowski L. (1999), Sieci neuronowe, algorytmy genetyczne i systemy rozmyte, PWN, Warszawa.
  • 14. Shore B. (2008), Systematic biases and culture in project failures, Project Management Journal, vol. 39, ss. 5-16.
  • 15. Spałek S. (2004), Krytyczne czynniki sukcesu w zarządzaniu projektami, Wydawnictwo Politechniki Śląskiej, Gliwice.
  • 16. Szyjewski Z. (2004), Metodyki zarządzania projektami informatycznymi, Placet, Warszawa.
  • 17. Trocki M., Grucza B., Ogonek K. (2009), Zarządzanie projektami, PWE, Warszawa.
  • 18. Van Roy P., Haridi S. (2004), Concepts, techniques and models of computer programming, MIT Press, Massachusetts.
  • 19. www.mozart-oz.org/data dostępu 21.01.2012.
Typ dokumentu
Bibliografia
Identyfikator YADDA
bwmeta1.element.baztech-article-BPZ4-0023-0016
JavaScript jest wyłączony w Twojej przeglądarce internetowej. Włącz go, a następnie odśwież stronę, aby móc w pełni z niej korzystać.