Zaawansowany model niwelacji zapotrzebowania na środki do produkcji w realizacji robót budowlanych
Języki publikacji
Abstrakty
The fluctuation of required resources causes problems in construction scheduling. Thus, researchers have developed resource leveling techniques to minimize the deviation between the resource requirements and the desired resource profile. However, the resource leveling problem cannot be solved with exact optimization methods except for small size scheduling problems because it is defined as a discrete combinatorial problem. Therefore, researchers have used heuristic approaches to get an acceptable solution that may not necessarily be optimal. This paper presents a multi-heuristic model for the solution of resource leveling problems. The initial computational results indicate that this heuristic model produces reasonably good solutions. In addition, the multi-heuristic model is a viable approach for complex scheduling networks.
Fluktacja zapotrzebowania na środki do produkcji w realizacji robót budowlanych powoduje trudności w ustalaniu harmonogramów pracy na placu budowy. Zostały wynalezione w tym celu sposoby algorytmiczno-heurystyczne niwelacji różnic w zapotrzebowaniu na środki. Artykuł niniejszy przedstawia model wieloheurystyczny rozwiązania zagadnienia niwelacji zapotrzebowania na środki do produkcji. Wstępne doświadczenia obliczeniowe wskazują na możliwość uzyskiwania dobrych wyników. Model wieloheurystyczny daje poza tym możliwość zastosowania go przy wykorzystaniu skomplikowanych modeli sieciowych harmonogramów pracy w budownictwie.
Czasopismo
Rocznik
Tom
Strony
47--54
Opis fizyczny
Bibliogr. 12 poz.
Twórcy
autor
autor
- Department of Civil and Environmental Engineering, University of Nevada, Las Vegas, NV 89154-4015, U. S. A.
Bibliografia
Typ dokumentu
Bibliografia
Identyfikator YADDA
bwmeta1.element.baztech-article-BPB1-0002-0015