Impact of baseline terms on the course of critical paths and time buffers in the modified Goldratt’s method

Treść / Zawartość
Identyfikatory
Warianty tytułu
Języki publikacji
EN
Abstrakty
EN
The introduction of a baseline term to the dependency network most often results in a change, break and/or generation of a new sequence of critical path, depending on the type of such a baseline term and the exact date selected. Each of those situations has an impact on the location or need to include new time buffers in the modified Goldratt’s method. The purpose of this article was to identify possible effects brought by declaration of each type of baseline term and to point out actions to be taken in each case. It must be noted that guidelines provided should in each individual case be adapted to the specific character of schedule changes caused by implementation of the relevant baseline term. The example presented herein exemplifi es one of such solutions to be implemented as a result of break of the critical path and need to introduce new time buffers.
Rocznik
Strony
313--320
Opis fizyczny
Bibliogr. 8 poz., il., tab.
Twórcy
  • Division of Technologies and Organization of Engineering Works, Warsaw University of Life Sciences
  • Division of Technologies and Organization of Engineering Works, Warsaw University of Life Sciences
Bibliografia
  • 1 Chatfield C., Johnson T., Microsoft Office Project 2007 Step by step [in Polish], RM, Warszawa, 2008
  • 2 Goldratt E. M., Critical Chain , The North River Press 1997 P.O. Box 567.
  • 3 Leśniak A., Plebankiewicz E., Zima K. 2012 Design and build procurement system – contractor selection. Archives of Civil Engineering. Volume LVIII, Issue 4, Pages 463–476.
  • 4 Połoński M. 2010, How to calculate dates and slack time in PDM diagram with different relationship types between tasks [in Polish] Scientific Review Engineering and Environmental Sciences 2 (48) p. 60-74.
  • 5 Połoński M, Pruszyński K., 2008, The time buffers location and critical chain concepts in civil engineering network schedule. Part I. Theoretical background. [in Polish] Przegląd Budowlany 2008, no. 2, p. 45–49.
  • 6 Połoński M, Pruszyński K. 2008, The time buffers location and critical chain concepts in civil engineering network schedule. Part II. Practical application [in Polish]. Przegląd Budowlany 2008, no. 3, p. 55–62.
  • 7 Skorupka D. 2005 The method of identification and quantification of construction project risk, Archives of Civil Engineering. Volume LI, Issue 4, Pages 647–662.
  • 8 Wilczewski S., Ms Project 2007 I Ms Project Server 2007. Successful project management [in Polish] Efektywne zarządzanie projektami, Wyd. Helion, Gliwice 2007.
Typ dokumentu
Bibliografia
Identyfikator YADDA
bwmeta1.element.baztech-986d82cd-44fb-4c69-a79d-a4c32a6daa62
JavaScript jest wyłączony w Twojej przeglądarce internetowej. Włącz go, a następnie odśwież stronę, aby móc w pełni z niej korzystać.