Project cost and time key factors distressing building construction projects of Sindh Pakistan: a post-pandemic approach

Treść / Zawartość
Identyfikatory
Warianty tytułu
Języki publikacji
EN
Abstrakty
EN
The construction industry plays a major role in the boost of the country’s economy, providing basic facilities for residential and creating thousands of job opportunities. During COVID-19, the construction sectors in Sindh Pakistan was highly suffered and leading to delays in the completion of projects. As the construction sector was globally affected, building construction projects were also affected by completing the projects on estimated time and cost. Thus, this research investigates the significant factors of time and cost that affected the Hyderabad building construction projects during COVID-19 situation. Questionnaire surveys were designed to collect data from the employees working on building projects in Sindh Pakistan. The collected data was analyzed through the Average Index method. Unsafe working environment; shortage of workers; and increasing project cost was observed as significant factors that were highly affected during COVID-19. The results and findings shall be supportive for stakeholders to take into consideration of factors in the early stage of the expected pandemic situation. This research suggested that the stakeholders shall modify or amend the contract clause regarding for pandemic situation and incorporate the identified factors in the contract that should be considered by stakeholders to save the time and cost of the projects.
Słowa kluczowe
Rocznik
Strony
591--602
Opis fizyczny
Bibliogr. 22 poz., il., tab.
Twórcy
  • Jamilus Research Center, Faculty of Civil Engineering & Environmental Engineering, University Tun Hussein Onn Malaysia, Batu Pahat, Malaysia (student)
  • Jamilus Research Center, Faculty of Civil Engineering & Environmental Engineering, University Tun Hussein Onn Malaysia, Batu Pahat, Malaysia
  • Department of Engineering Management, College of Engineering, Prince Sultan University, Riyadh, Saudi Arabia
Bibliografia
  • [1] A.Q. Memon, A.H. Memon, M.A. Soomro, and I.A. Rahman, “Common factors affecting time and cost performance of construction projects in Pakistan”, Pakistan Journal of Science, vol. 71, pp. 64-68, 2019.
  • [2] S. Hussain, F. Zhu, Z. Ali, H.D. Aslam, and A. Hussain, “Critical delaying factors: public sector building projects in Gilgit-Baltistan, Pakistan”, Buildings, vol. 8, no. 1, 2018, doi: 10.3390/buildings8010006.
  • [3] F.A. Soomro, M.J. Memon, A.F. Chandio, S. Sohu, and R. Soomro, “Causes of time overrun in construction of building projects in Pakistan”, Engineering, Technology & Applied Science Research, vol. 9, no. 1, pp. 3762-3764, 2019, doi: 10.48084/etasr.2449.
  • [4] A.Q. Memon, A.H. Memon, and M.A. Soomro, “Mitigating resource management related factors affecting time and cost performance in construction projects”, Pakistan Journal of Engineering Technology, vol. 4, no. 2, pp. 62-66, 2021, doi: 10.51846/vol4iss2pp62-66.
  • [5] S. Sohu, A.H. Abdullah, S. Nagapan, N.A. Memon, R. Yunus, and M.F. Hasmori, “Causative factors of cost overrun in building projects of Pakistan”, International Journal of Intergrated Engineering, vol. 10, no. 9, pp. 23-27, 2018, doi: 10.30880/ijie.2018.10.09.005.
  • [6] M.A. Akhund and A.H. Memon, “Causative factors of time overrun in constrution projects of causative factors of time overrun in constrution projects of Sindh”, presented at 6th International Conference on Environment Sustainability Development At: Comsat University, Abbotabad, July 2018, pp. 1-7.
  • [7] F. Sohil, M.U. Sohail, and J. Shabbir, “COVID-19 in Pakistan: challenges and priorities”, Cogent Medicine, vol. 8, no. 1, art. no. 1966179, 2021, doi: 10.1080/2331205x.2021.1966179.
  • [8] G. Azeem, M. Mirmozaffari, R. Yazdani, and R.A. Khan, “Exploring the impacts of Covid-19 pandemic on risks faced by infrastructure projects in Pakistan”, International Journal of Applied Decision Sciences, vol. 15, no. 2, pp. 181-200, 2022, doi: 10.1504/IJADS.2022.121558.
  • [9] S.P. Timilsina, S.K. Ojha, and B.R. Dhungana, “Impact of Covid-19 on construction industry of Nepal”, Modern Economy, vol. 12, no. 8, pp. 1232-1244, 2021, doi: 10.4236/me.2021.128064.
  • [10] H.H. Shaikh, N.Y. Zainun, and S.H. Khahro, “Timely identification of claims in construction industry: a blessing in disguise”, International Journal of Advanced Science and Technology, vol. 29, no. 9, pp. 7050-7056, 2020.
  • [11] D. Larasati, N. Ekawati, S. Triyadi, A.F. Muchlis, and A. Wardhani, “Impact of the pandemic COVID-19 on the implementation of construction contracts”, IOP Conference Series: Earth and Environmental Science, vol. 738, 2021, doi: 10.1088/1755-1315/738/1/012075.
  • [12] S.H. Zamani, R.A. Rahman, M.A. Fauzi, and L.M. Yusof, “Effect of COVID-19 on building construction projects: impact and response mechanisms”, IOP Conference Series: Earth and Environmental Science, vol. 682, 2021, doi: 10.1088/1755-1315/682/1/012049.
  • [13] Y. Gamil and A. Alhagar, “The impact of pandemic crisis on the survival of construction industry: a case of COVID-19”, Mediterranean Journal of Social Sciences, vol. 11, no. 4, 2020, doi: 10.36941/mjss-2020-0047.
  • [14] M. Akram, T.H. Ali, N.A. Memon, and S.H. Khahro, “Causal attributes of cost overrun in construction projects of Pakistan”, International Journal of Civil Engineering and Technology, vol. 8, no. 6, pp. 477-483, 2017.
  • [15] System Creative Research, “Creative Research Systems”. [Online]. Available: www.surveysystem.com. [Accessed: 08. June 2022].
  • [16] K.S. Taber, “The use of Cronbach’s Alpha when developing and reporting research instruments in science education”, Research in Science Education, vol. 48, no. 6, pp. 1273-1296, 2018, doi: 10.1007/s11165-016-9602-2.
  • [17] A. Pamidimukkala and S. Kermanshachi, “Impact of Covid-19 on field and office workforce in construction industry”, Project Leadership and Society, vol. 2, art. no. 100018, 2021, doi: 10.1016/j.plas.2021.100018.
  • [18] S. Sumra, M.S. Shahbaz, P. Kumar, and S. Sohu, “Are the current supply chain management practices enough for innovation?”, International Journal of Disaster Recovery and Business Continuity, vol. 11, no. 1, pp. 2413-2428, 2020.
  • [19] S. Sumra, H. Shaikh, and S. Shaikh, “Employee motivation: a comparative analysis of Banora Textile and Sapphire Textile Mills by applying applications of two-factor theory”, International Journal of Scientific & Engineering Research, vol. 10, no. 4, pp. 1035-1039, 2019.
  • [20] T. Al Amri and M. Marey-Pérez, “Impact of Covid-19 on Oman’s construction industry”, Technium Social Sciences Journal, vol. 9, pp. 661-670, 2020, doi: 10.47577/tssj.v9i1.1021.
  • [21] S. Khahro, T.H. Ali, A.A. Vighio, Q.H. Khahro, and M.A. Moriyani, “Post pandemic project management key skills and challenges”, Talent Development & Excellence, vol. 12, no. 3, pp. 2253-2260, 2020.
  • [22] S.H. Khahro and Z.A. Memon, “Non excusable delays in construction industry: a causal study”, Engineering, Technology & Applied Science Research, vol. 8, no. 6, pp. 3561-3564, 2018, doi: 10.48084/etasr.2335.
Uwagi
Opracowanie rekordu ze środków MNiSW, umowa nr SONP/SP/546092/2022 w ramach programu "Społeczna odpowiedzialność nauki" - moduł: Popularyzacja nauki i promocja sportu (2024).
Typ dokumentu
Bibliografia
Identyfikator YADDA
bwmeta1.element.baztech-743ea3c9-65a0-4ea7-b85e-423721236da4
JavaScript jest wyłączony w Twojej przeglądarce internetowej. Włącz go, a następnie odśwież stronę, aby móc w pełni z niej korzystać.