Enterprise's risk assessment of complex construction projects

Autorzy
Treść / Zawartość
Identyfikatory
Warianty tytułu
PL
Ocena ryzyka inwestycyjnego w złożonych przedsięwzięciach budowlanych
Języki publikacji
EN
Abstrakty
EN
The purpose of this article is to present the preparation of Project Risk Assessment Methodology and its mitigation in complex construction projects. The main text provides a summary of the approach, the method used and the findings. The conclusions have been drawn that the proper tools for quantifying risks have to be based on the criteria specific for mathematical statistic and probability or at least fuzziness. Function, which makes possible to categorize any risks into one of the five categories, is a combination of probability and the impact on one of the items: people and their safety or budget, cost, schedule and planning or quality and performance. An attempt was made to express numerically the relationship between risks impacts and their level of likelihood. Also, a method of associating the influence of projects risks impacts on the extent of the likelihood of project risk occurrence which makes possible to determine the direction and the strength of this relationship was presented.
PL
Ryzyko przedsięwzięcia budowlanego jest definiowane jako nieplanowane zdarzenie, które – jeśli wystąpi – ma negatywny wpływ na cel zadania inwestycyjnego. Na podstawie tej definicji przedstawiono narzędzia do kwantyfikacji ryzyk, oparte na założeniach matematycznych i kryteriach probabilistycznych. Funkcja - która umożliwia kategoryzowanie wszelkich ryzyk w jedną z pięciu kategorii - jest kombinacją prawdopodobieństwa wystąpienia ryzyka i jego wpływu na: ludzi i ich bezpieczeństwo, budżet i nakłady inwestycji, planowanie i harmonogramowanie przedsięwzięcia oraz jakość realizacji robót budowlanych. W artykule przedstawiono próbę liczbowego wyrażenia relacji pomiędzy wielkością ryzyk a prawdopodobieństwem ich wystąpienia. Zaprezentowano metodę powiązania wpływu wagi ryzyka z prawdopodobieństwem jego wystąpienia jako zdarzenia losowego oraz wyznaczenia kierunku i siły tego związku w przedsięwzięciach budowlanych.
Rocznik
Strony
63--74
Opis fizyczny
Bibliogr. 16 poz., il., tab.
Twórcy
autor
  • Wroclaw University of Technology, Faculty of Civil Engineering, Department of Construction Methods and Management, Wrocław
Bibliografia
  • 1. Abdul-Rahman H., Wang Ch., Y. L. “Design and pilot run of fuzzy synthetic model (FSM) for risk evaluation in civil engineering”, Journal of Civil Engineering and Management, 2013, pp. 217-238.
  • 2. Almeida N. M., Sousa V., Dias L. A., Branco F., “Engineering risk management in performance-based building environments”, Journal of Civil Engineering and Management 2015, pp. 218-230.
  • 3. Almeida N. M., Sousa V., Dias L. A., Branco F., “Managing the technical risk of performance-based building structures”, Journal of Civil Engineering and Management 2015, pp. 384-394.
  • 4. Akintoye, A. S., Malcolm J., ”Risk analysis and management in construction”, International Journal of Project Management, 1997, 15.1, pp. 31-38.
  • 5. Chi S., Han S., Kim D. Y., Shin Y. “Accident risk identification and its impact analyses for strategic construction safety management”, Journal of Civil Engineering and Management 2015,pp. 524-538.
  • 6. Edwards, P. J.; Bowen, P. A., “Risk and risk management in construction: a review and future directions for research”, Engineering, Construction and Architectural Management, 1998, 5.4, pp. 339-349
  • 7. Ibadov N., Kulejewski J., “The assessment of construction project risks with the use of fuzzy sets theory”, Technical Transactions, Cracow University of Technology, 2014, , pp. 175-182 .
  • 8. Kacprzyk J., “Fuzzy sets in systematic analysis”, PWN, Warsaw 1986, pp. 25-28, 67-72
  • 9. Konior J., ”Risk management in PM Group Polska. Quality Management System”, PM Group, Ireland, 2003-2015
  • 10. Mak, S.; Picken, D., “Using risk analysis to determine construction project contingencies”, Journal of Construction Engineering and Management, 2000, 126.2: 130-136.
  • 11. Morrison D. F., “Multivariate statistical methods”, McGraw - Hill Book Company, New York 1990, pp. 121-123
  • 12. Silvestre J. D., Silva A., de Brito J., “Uncertainty modelling of service life and environmental performance to reduce risk in building design decisions”, Journal of Civil Engineering and Management 2015, pp. 308-322
  • 13. Skorupka D., “Identification and initial risk assessment of construction projects in Poland”, Journal of Management in Engineering, 2008, pp. 120-127.
  • 14. Ward, S. C.; Chapman, C. B., “Risk management perspective on the project lifecycle”, International Journal of Project Management, 1995, 13.3, pp. 145-149.
  • 15. Yu J., Jeon M., Kim T. W., “Fuzzy-based composite indicator development methodology for evaluating overall project performance”, Journal of Civil Engineering and Management 2015, pp. 343-355.
  • 16. Zavadskas E.K, , Turskisb Z., Tamošaitienec J., “Risk assessment of construction projects”, Journal of Civil Engineering and Management 2010, pp. 33-46.