Concept of installation of cable terminations on 110-400 kV live line poles

Autorzy
Identyfikatory
Warianty tytułu
PL
Koncepcja montażu pod napięciem głowic kablowych końcowych na słupach linii 110-400 kV
Języki publikacji
EN
Abstrakty
EN
Modernization and reconstruction projects of overhead lines, ranging between 110 kV and 400 kV, are related to intensive expansion of infrastructure in our country in recent years. It applies in particular to construction of roads, railroads, sports and cultural facilities, including highways, sports stadiums, which leads to installation of cables on various lengths of sections, which frequently enter dense built-up areas of urban agglomerations. Expanded infrastructure, formal-legal regulations cause difficulties to acquire land for overhead lines. Therefore, despite higher costs, projects involve installation of 110kV-400kV cable lines more often than in the past. The most frequent projects involve construction of 110kV cable lines, which cost is nearly twice as high as overhead lines. Installation of cable lines requires high quality installation works, including heads on line poles and support structures of stations. In order to avoid inconvenient outages, electrical companies conduct concept works in order to install heads on live lines. These works are described in this paper. It discusses the principles of occupational safety and the risk involved in this type of works.
PL
Projekty modenizacji i rekonstrukcji linii napowietrznych 110-400 kV są związane z intensywnym rozwojem infrastruktury w naszym kraju w ostatnich latach. Dotyczy to w szczególności budowy dróg, linii kolejowych, obiektów sportowych i kulturalnych i prowadzi do konieczności instalowania linii kablowych o różnej długości, które często wchodzą w gęstą zabudowę miejską. Rozwijająca się infrastruktura, jak i przepisy formalno-prawne, powodują trudności w pozyskaniu przestrzeni pod linie napowietrzne. Tak więc, pomimo wyższych kosztów, projekty oparte na zastosowaniu linii kablowych 110-400 kV są opracowywane dużo częściej niż w przeszłości, przy czym najczęściej oparte są one o linie kablowe 110 kV, których koszt budowy jest prawie dwa razy większych niż odpowiadające im linie napowietrzne. Pamiętać przy tym należy, że budowa linii kablowych wymaga prowadzenia prac instalacyjnych o wysokiej jakości, włączając w to głowice przyłączeniowe na słupach i struktury podtrzymujące stacje. W celu uniknięcia długotrwałych wyłączeń sieci, firmy energetyczne prowadzą prace koncepcyjne nad instalacją głowic przy pomocy technologii PPN, i te właśnie prace są opisane w niniejszym artykule. Omówione są także zasady bezpieczeństwa zawodowego i zagrożenia związane z zastosowaniem tego typu technologii.
Czasopismo
Rocznik
Tom
Strony
470--474
Opis fizyczny
Bibliogr. 12 poz., rys., tab.
Twórcy
autor
  • Production Director MEGA-POL S.A.
autor
  • PKBwE SEP - Poland
Bibliografia
  • [1] B. Dudek, S. Widlas.: Modern technology of electrical equipment maintenance – live-line working in Poland, CIGRE Regional, RSEEC 2012 Innovation for future! Section E Live Working, Sibiu, Romania 2012 p.38-47
  • [2] Z. Gacek, B. Dudek: Getting closer to electrical equipment – analysis of safe distances in practice, according to experiences in the country and abroad, Materials for the 10th Conference – Live-live working on low-, medium- and high-voltage power grids in Poland and the world, Łódź, 2010
  • [3] T. Musiał: Single- and double-circuit 110 kV lines – cable-overhead connections with the use of pipe poles
  • [4] E. Gulski, A. Rakowska, K. Siodła, P. Chojnowski: Role of operation testing and diagnostics of high-voltage power transmission cables with the use of sensitive measurement methods and diagnostics of high-voltage power transmission cables with the use of sensitive measurement methods
  • [5] R. Nowicki, D. Słowiński: Selected issues related to 110 kV cable line design, 8th Conference on power cable lines – present condition, new techniques, PTPiREE Łódź 2011
  • [6] S. Widlas: Construction of 110 kV cable line along with fiber-optic routing for powering the National Stadium in Warsaw, 8th Conference on power cable lines – present condition, new techniques, PTPiREE, Łódź 2011
  • [7] B. Kubacki: Cabling of existing high- and low-voltage overhead lines. 220 kV cable line design – station (400kV)/220 kV/ 110 kV Świebodzice, 8th Conference on power cable lines – present condition, new techniques, PTPiREE, Łódź 2011
  • [8] A. Cichy: Installation of high-voltage cable lines based on experiences of Tele-Fonika Kable, 19th Training – Technical Conference KABEL 2012, Zakopane 2012
  • [9] E. Gulski, A. Rakowska, K. Siodła: Advanced methods for performance of voltage testing and diagnosis of the condition of high-voltage cable lines, 8th Conference on power cable lines – present condition, new techniques, PTPiREE, Łódź 2011
  • [10] G. Kochan, B. Dudek: Use of temporary line as an element for optimization of work of the transmission grid, Spektrum no. 9-10, 2012
  • [11] Dudek B., Widlas S.: Concept of Installation of Cable Heads on 110-400 kV Live Line Poles, Ref. 027 CITTES’2013, Concordia, Argentina
  • [12] Rozporządzenie Ministra Gospodarki z dnia 28 marca 2013 r. w sprawie bezpieczeństwa i higieny pracy przy urządzeniach energetycznych (Dz.U. z dn. 23 kwietnia 2013, poz. 492)
Typ dokumentu
Bibliografia
Identyfikator YADDA
bwmeta1.element.baztech-0d771924-fecc-4fe5-a721-40ef40e92cfa