S-modeS-model for project cost management in value engineering for construction companies

Treść / Zawartość
Identyfikatory
Warianty tytułu
Języki publikacji
EN
Abstrakty
EN
Today’s fast-changing environment for construction companies requires rapid responses and adaptation of their projects. Despite the multitude of tools applied for project cost management in engineering and construction companies, there is a need to form comprehensive solutions. The purpose of the study is to form a methodological approach to project cost management in the field of engineering construction based on alternative models to diagnose the development, assessment and selection of functional areas and content of cost management in the construction project, which allows one to increase adaptability and flexibility in the process of its implementation. The basis of research methodology is modeling, which allows one to adjust the economic and financial flows based on three S-curves, one for each component of the total cost of the work: direct costs, indirect costs and reserves. These curves include the direct cost curve for the main purchasing packages as well. This brings financial flows closer to reality because it is possible to adjust the S-curves according to the behavior of each subsystem. The contribution of the study is the proposed approach of integrating concepts related to the coordination and development of project design and production management (lean construction), forming a “3D model of management”, in a broad and comprehensive management system. It assumes a comprehensive and complete way to manage civil engineering projects. The proposed methodological approach can make a significant contribution to the preparation of forecasts and estimates by planners and controllers in the context of construction projects.
Rocznik
Strony
art. no. e146617
Opis fizyczny
Bibliogr. 45 poz., rys., tab.
Twórcy
autor
  • Department of Construction Engineering, Xinxiang Vocational and Technical College, Xinxiang, China
  • Faculty of Economics and Management, Sumy National Agrarian University, Sumy, Ukraine
autor
  • Faculty of Economics and Management, Sumy National Agrarian University, Sumy, Ukraine
  • Funding Center, Education Bureau of Hongqi District, Xinxiang City, China
  • Department of Marketing and Logistics, Sumy National Agrarian University, Sumy, Ukraine
autor
  • Faculty of Economics and Management, Sumy National Agrarian University, Sumy, Ukraine
  • Personnel Department, Henan Expressway Monitoring Toll Communication Network Service Co. Ltd., Zhengzhou, China
Bibliografia
  • [1] A. Ebekozien and C. Aigbavboa, “COVID-19 recovery for the Nigerian construction sites: the role of the fourth industrial revolution technologies,” Sust. Cities Soc., vol. 69, p. 102803, 2021, doi: 10.1016/j.scs.2021.102803.
  • [2] Y. Chen, “Integrated and intelligent manufacturing: perspectives and enablers,” Engineering, vol. 3, no. 5, pp. 588–595, 2017, doi: 10.1016/J.ENG.2017.04.009.
  • [3] R. Yanita and K. Mochtar, “Legal aspect of value engineering implementation in Jakarta (Indonesia) construction projects,” Int. J. Constr. Manag., vol. 21, no. 2, pp. 131–139, 2021, doi: 10.1080/15623599.2018.1511946.
  • [4] E.M.A.C. Ekanayake and Y.G. Sandanayake, “LiVE approach: lean integrated value engineering for construction industry,” Built Envir. Proj. Asset Manag., vol. 7, no. 5, pp. 518–533, 2017, doi: 10.1108/BEPAM-11-2016-0071.
  • [5] E. Oey and J. Lim, “Challenges and action plans in construction sector owing to COVID-19 pandemic–a case in Indonesia real estates,” Int. J. Lean Six Sigma, vol. 12, no. 4, pp. 835–858, 2021, doi: 10.1108/IJLSS-09-2020-0149.
  • [6] C. Amoah, E. Bamfo-Agyei, and F. Simpeh, “The COVID-19 pandemic: the woes of small construction firms in Ghana,” Smart Sust. Built Envir., vol. 11, no. 4, pp. 1099–1115, 2022, doi: 10.1108/SASBE-02-2021-0025.
  • [7] G.K. Koulinas, P.K. Marhavilas, O.E. Demesouka, A.P. Vavatsikos, and D.E. Koulouriotis, “Risk analysis and assessment in the worksites using the fuzzy-analytical hierarchy process and a quantitative technique–a case study for the Greek construction sector,” Safety Sci., vol. 112, pp. 96–104, 2019, doi: 10.1016/j.ssci.2018.10.017.
  • [8] P. Shojaei and S.A.S. Haeri, “Development of supply chain risk management approaches for construction projects: a grounded theory approach,” Comp. Ind. Eng., vol. 128, pp. 837–850, 2019, doi: 10.1016/j.cie.2018.11.045.
  • [9] J. Novitasari and R.A. Rahadi, “Evaluation of property investment (case of buy or build commercial office building in Jakarta’s CBD area),” Europ. J. Bus. Manag. Res., vol. 7, no. 4, pp. 116–120, 2022, doi: 10.24018/ejbmr.2022.7.4.1423.
  • [10] S.R. Jadhav and S.V. Joshi, “Implementation of value engineering in construction management,” J. Int. Design. Reg. Plan., vol. 7, no. 1, pp. 34–42, 2022.
  • [11] R. Janani, P.K. Chakravarthy, and D.R.R. Raj, “A study on value engineering & green building in residential construction,” Int. J. Civ. Eng. Tech., vol. 9, no. 1, pp. 900–907, 2018.
  • [12] E. M. A. C. Ekanayake, G. Shen, and M. M. Kumaraswamy, “Mapping the knowledge domains of value management: a bibliometric approach,” Eng. Constr. Archit. Manag., vol. 26, no. 3, pp. 499–514, 2019, doi: 10.1108/ECAM-06-2018-0252.
  • [13] I. Othman, A.F. Kineber, A.E. Oke, T. Zayed, and M.K. Buniya, “Barriers of value management implementation for building projects in Egyptian construction industry,” Ain Shams Eng. J., vol. 12, no. 1, pp. 21–30, 2021, doi: 10.1016/j.asej.2020.08.004.
  • [14] P. Wu, Y. Xu, R, Jin, Q, Lu, D. Madgwick, and C.M. Hancock, “Perceptions towards risks involved in off-site construction in the integrated design & construction project delivery,” J. Clean. Prod., vol. 213, pp. 899–914, 2019, doi: 10.1016/j.jclepro.2018.12.226.
  • [15] Z. Ahmad, M.J. Thaheem, and A. Maqsoom, “Building information modeling as a risk transformer: an evolutionary insight into the project uncertainty,” Autom. Constr., vol. 92, pp. 103–119, 2018, doi: 10.1016/j.autcon.2018.03.032.
  • [16] M. Calahorra-Jimenez, C. Torres-Machi, A. Chamorro, L.F. Alarcón, and K. Molenaar, “Importance of noncost criteria weighing in best-value design–build US highway projects,” J. Manag. Eng., vol. 37, no. 4, p. 04021027, 2021, doi: 10.1061/(asce)me.1943-5479.0000912.
  • [17] H. Danso and R. Osei Kwadwo, “Assessment of value engineering implementation in the Ghanaian construction sector,” J. Instit. Eng. (India): Ser. A, vol. 101, no. 1, pp. 7–17, 2020, doi: 10.1007/s40030-019-00423-6.
  • [18] T. Tan, K. Chen, F. Xue, and W. Lu, “Barriers to Building Information Modeling (BIM) implementation in China’s prefabricated construction: an interpretive structural modeling (ISM) approach,” J. Clean. Prod., vol. 219, pp. 949–959, 2019, doi: 10.1016/j.jclepro.2019.02.141.
  • [19] S.D. Green and N. Sergeeva, “Value creation in projects: towards a narrative perspective,” Int. J. Proj. Manag., vol. 37, no. 5, pp. 636–651, 2019, doi: 10.1016/j.ijproman.2018.12.004.
  • [20] M. Marzouk, S. Azab, and M. Metawie, “BIM-based approach for optimizing life cycle costs of sustainable buildings,” J. Clean. Prod., vol. 188, pp. 217–226, 2018, doi: 10.1016/j.jclepro.2018.03.280.
  • [21] Y. Zhai et al., “An Internet of Things-enabled BIM platform for modular integrated construction: a case study in Hong Kong,” Adv. Eng. Inform., vol. 42, p. 100997, 2019, doi: 10.1016/j.aei.2019.100997.
  • [22] M. Sutrisna and J. Goulding, “Managing information flow and design processes to reduce design risks in offsite construction projects,” Eng. Constr. Archit. Manag., vol. 26, no. 2, pp. 267–284, 2019.
  • [23] J. Beckert, “Markets from meaning: quality uncertainty and the intersubjective construction of value,” Cambr. J. Econ., vol. 44, no. 2, pp. 285–301, 2020, doi: 10.1093/cje/bez035.
  • [24] D. Muntu, R. Setyawati, L.S. Riantini, and M. Ichsan, “Effect of human resources management and advances to improve construction project performance,” Phys. Chem. Earth, Parts A/B/C, vol. 122, p. 103000, 2021, doi: 10.1016/j.pce.2021.103000.
  • [25] J. Varajão, G. Fernandes and H. Silva, “Most used project management tools and techniques in information systems projects,” J. Syst. Inform. Techn., vol. 22, no. 3, pp. 225–242, 2020, doi: 10.1108/JSIT-08-2017-0070.
  • [26] D. Heigermoser, B.G. de Soto, E.L.S. Abbott, and D.K.H. Chua, “BIM-based Last Planner System tool for improving construction project management,” Autom. Constr., vol. 104, pp. 246–254, 2019, doi: 10.1016/j.autcon.2019.03.019.
  • [27] R. Bortolini, C.T. Formoso, and D.D. Viana, “Site logistics planning and control for engineer-to-order prefabricated building systems using BIM 4D modeling,” Autom. Constr., vol. 98, pp. 248–264, 2019, doi: 10.1016/j.autcon.2018.11.031.
  • [28] K. Hussain, Z. He, N. Ahmad, and M. Iqbal, “Green, lean, six sigma barriers at a glance: a case from the construction sector of Pakistan,” Build. Envir., vol. 161, p. 106225, 2019, doi: 10.1016/j.buildenv.2019.106225.
  • [29] Z. You and C. Wu, “A framework for data-driven informatization of the construction company,” Adv. Eng. Inform., vol. 39, pp. 269–277, 2019, doi: 10.1016/j.aei.2019.02.002.
  • [30] W. Kittinaraporn, S. Tuprakay, and L. Prasittisopin, “Effective modeling for construction activities of recycled aggregate concrete using artificial neural network,” J. Constr. Eng. Manag., vol. 148, no. 3, p. 04021206, 2022, doi: 10.1061/(ASCE)CO.1943-7862.0002246.
  • [31] Y. Liu, X. Wang, and D. Wang, “How leaders and coworkers affect construction workers’ safety behavior: an integrative perspective,” J. Constr. Eng. Manag., vol. 147, no. 12, p. 04021176, 2021, doi: 10.1061/(asce)co.1943-7862.0002215.
  • [32] L.A.L. Ruiz, X.R. Ramón, and S.G. Domingo, “The circular economy in the construction and demolition waste sector – a review and an integrative model approach,” J. Clean. Prod., vol. 248, p. 119238, 2020, doi: 10.1016/j.jclepro.2019.119238.
  • [33] I.P. Serrado, J.A. Santos, N.L. de Oliveira, and A.P. Freitas, “Identification of importance levels of market risks in the construction sector,” J. Eng. Proj. Prod. Manag., vol. 9, no. 2, pp. 74–84, 2019, doi: 10.2478/jeppm-2019-0009.
  • [34] J. Liu, Z. Wang, M. Skitmore, and L. Yan, “How contractor behavior affects engineering project value-added performance,” J. Manag. Eng.-ASCE, vol. 35, no. 4, p. 04019012, 2019, doi: 10.1061/(ASCE)ME.1943-5479.0000695.
  • [35] A. Toppinen, N. Miilumäki, H. Vihemäki, R. Toivonen, and K. Lähtinen, “Collaboration and shared logic for creating value-added in three Finnish wooden multi-storey building projects,” Wood Mater. Sci. Eng., vol. 14, no. 5, pp. 269–279, 2019, doi: 10.1080/17480272.2019.1653365.
  • [36] S.E.D.A. Rehim, N.A. Mostafa, and T.A. Mohamed, “Adjusting the logistic function to develop a more realistic product life cycle model,” Int. J. Prod. Lifecycle Manag., vol. 13, no. 3, pp. 205–223, 2021, doi: 10.1504/ijplm.2021.10039405.
  • [37] D. Walker and B. Lloyd-Walker, “The future of the management of projects in the 2030s,” Int. J. Manag. Proj. Bus., vol. 12, no. 2, pp. 242–266, 2018, doi: 10.1108/IJMPB-02-2018-0034.
  • [38] T.S. Omotayo, P. Boateng, O. Osobajo, A. Oke, and L.I. Obi, “Systems thinking and CMM for continuous improvement in the construction industry,” Int. J. Prod. Perform. Manag., vol. 69, no. 2, pp. 271–296, 2019, doi: 10.1108/IJPPM-11-2018-0417.
  • [39] R.M. Johnson and R.I.I. Babu, “Time and cost overruns in the UAE construction industry: a critical analysis,” Int. J. Constr. Manag., vol. 20, no. 5, pp. 402–411, 2020, doi: 10.1080/15623599.2018.1484864.
  • [40] J.B.H. Yap, I.N. Chow, and K. Shavarebi, “Criticality of construction industry problems in developing countries: analyzing Malaysian projects,” J. Manag. Eng., vol. 35, no. 5, p. 04019020, 2019, doi: 10.1061/(asce)me.1943-5479.0000709.
  • [41] C.O. Cruz, P. Gaspar, and J. de Brito, “On the concept of sustainable sustainability: an application to the Portuguese construction sector,” J. Build. Eng., vol. 25, p. 100836, 2019, doi: 10.1016/j.jobe.2019.100836.
  • [42] F. Salleh, S. Palaniappan, I.L.P. Theng, H.N.M. Helmi, A. Abd Hamid, and N.M. Kassim, “A review on risk management implementation in the construction industry,” J. Crit. Rev., vol. 7, no. 11, pp. 562–567, 2020.
  • [43] F. Elghaish, S. Abrishami, S. Abu Samra, M. Gaterell, M.R. Hosseini, and R. Wise, “Cash flow system development framework within integrated project delivery (IPD) using BIM tools,” Int. J. Constr. Manag., vol. 21, no. 6, pp. 555–570, 2021, doi: 10.1080/15623599.2019.1573477.
  • [44] Z.M. Yaseen, Z.H. Ali, S.Q. Salih, and N. Al-Ansari, “Prediction of risk delay in construction projects using a hybrid artificial intelligence model,” Sustainability, vol. 12, no. 4, p. 1514, 2020.
  • [45] J. Patalas-Maliszewska, S. Kłos, and E. Dostatni, “Sustainable Business Model Integrated with the Enterprise Resource Planning system: SBM-ERP,” Bull. Pol. Acad. Sci. Tech. Sci., vol. 70, no. 6, p. e143829, 2022, doi: 10.24425/bpasts.2022.143829.
Uwagi
Opracowanie rekordu ze środków MNiSW, umowa nr SONP/SP/546092/2022 w ramach programu "Społeczna odpowiedzialność nauki" - moduł: Popularyzacja nauki i promocja sportu (2024).
Typ dokumentu
Bibliografia
Identyfikator YADDA
bwmeta1.element.baztech-0b765130-2026-4936-a2b1-8e912e46c247
JavaScript jest wyłączony w Twojej przeglądarce internetowej. Włącz go, a następnie odśwież stronę, aby móc w pełni z niej korzystać.